New Underground Electric Service System
- Closes
- September 28, 2026 · 13 days left
- Buyer
- National Capital Commission (NCC)
- Delivered in
- Canada-wide
- Reference
- NCC-CS-041053-NRFP
- Category
- Skilled trades
- Posted
- August 28, 2026
What the buyer is asking for
Install and energize a new main distribution cabinet and new Hydro Quebec (HQ) Site Service.
Provide the necessary power pedestals and connection points for temporary event connections.
Protect significant trees during the work and reinstate the park to an appropriate condition at the end of the
work.
This will maintain the current value and uses within the park and improve the functionality to provide
electrical power for major events in the future (including Winterlude).
Questions: contracts@ncc-ccn.ca